Data center capacity planning that ends in a date
Enter today's load, what your room or contract can carry and how fast you grow. The planner draws the forecast year by year, marks the month you cross your headroom line, and shows when the search for new capacity has to start and which limit gets there first.
Built for enterprise IT and infrastructure teams planning one to five years out. Every assumption carries its source and date.
Al Jazeera, Light Reading, Inc. and Fortune have quoted the team behind this planner.
- Runs out
- Nov 2028
- Decide
- Nov 2026 to May 2027
- Binding
- Power, 2N
The capacity planner
Enter what runs today, what the room or contract can carry and how fast you expect to grow. The chart redraws as you type, and your answers stay in this browser. Nothing is sent until you send the review request yourself.
How the planner works, and what it assumes
The planner runs one forecast a month for up to five years and compares each month with three limits: power, cooling and rack positions. These are the rules, and where each default comes from.
- Load today is measured, not nameplate. Enter what the UPS output or the rack PDUs read. Nameplate overstates real draw; Sunbird describes traditional planning as derating nameplate to about 70%, which is a rule of thumb, not a measurement (Sunbird DCIM blog (vendor), Mar 8, 2022).
- Usable power depends on redundancy. At N the whole installed figure counts. At N+1 one unit is held back. At 2N each path has to carry everything alone, so half the installed total is usable, the same 50% per side the BICSI study guide describes (BICSI DCDC study guide, continuous capacity management chapter, Oct 2026).
- Growth compounds. Your annual rate is applied month by month. The presets bracket the evidence: Dell Digital called 8% to 10% normal organic growth for its own estate (Dell Digital blog on T-shirt capacity sizing (vendor, internal case), about 2021), and Uptime's 2026 survey reports enterprise workloads growing 25% to 30% a year (Uptime Institute 2026 survey, reported by Data Center Knowledge, Jul 31, 2026).
- AI arrives as a step, not a rate. A GPU deployment lands in the month you choose, at the rack count and density you enter. Treating it as extra growth spreads it across years it does not occupy.
- The headroom line is a policy. The default is 80% of usable power and of cooling. Practice runs from 70% to 85%, and no standard fixes the number (BICSI DCDC study guide, continuous capacity management chapter, Oct 2026).
- Run-out is the first month a limit is reached. Power and cooling run out at the headroom line; space runs out when the racks you need fill every position you have.
- The decision window is 18 to 24 months before run-out, because that is how far ahead JLL says tenants now commit to colocation (JLL midyear 2025 data, reported by CoStar, Aug 18, 2025).
- The binding constraint is whichever limit comes first. This is the same minimum-of-limits logic OneUptime uses to count what a colocation rack can hold (OneUptime, estimating colocation rack capacity, Sep 7, 2026).
- Facility power uses PUE. The default of 1.52 is Uptime's 2026 industry average; the capacity-weighted average is 1.36, and large newer sites often run at 1.3 or lower (Uptime Intelligence, Update 518, Aug 6, 2026).
- Cooling for AI is flagged by density. Above about 50 kW a rack Uptime says air cooling becomes impractical (Data Center Knowledge, AI rack density feature, Aug 28, 2026), and CBRE says 100 kW GPU servers require closed-loop liquid (CBRE, North America Data Center Trends H1 2026, Aug 27, 2026).
The planner sells nothing. It names no facilities and no vendors, and no provider pays to appear in its colocation readout. Every visitor gets the same rules: they sit in one script, the wording in another, and both are published with the site.
The 2026 market your forecast runs into
A forecast that ends in colocation is only as good as the space available on the date it needs it. In 2026 that space is scarce, preleased early and getting more expensive every year.
| Measure | Figure | Source |
|---|---|---|
| Vacancy in primary North American markets | 1.4%, a record low, down from 1.6% a year earlier | CBRE, North America Data Center Trends H1 2026, Aug 27, 2026 |
| Capacity under construction already preleased | 80.4%, up from 74.3% | CBRE, North America Data Center Trends H1 2026, Aug 27, 2026 |
| Future capacity still available | Under 1,500 MW, about six months of demand | CBRE, North America Data Center Trends H1 2026, Aug 27, 2026 |
| North American vacancy, JLL's count | 1%, for the third year running | JLL, North America data center midyear 2026 release, Aug 11, 2026 |
| Capacity under construction already committed | 95% | JLL, North America data center midyear 2026 release, Aug 11, 2026 |
| Rent growth since 2020 | Nearly 70%, about 9% a year on average | JLL, North America data center midyear 2026 release, Aug 11, 2026 |
| How far ahead tenants commit | 18 to 24 months, against 6 to 12 before | JLL midyear 2025 data, reported by CoStar, Aug 18, 2025 |
| Wait for a new grid connection in primary markets | More than four years on average | JLL, 2026 Global Data Center Outlook, Jan 5, 2026 |
| Operators worried about power availability | 64% | Uptime Institute 2026 survey, reported by Data Center Knowledge, Jul 31, 2026 |
Cushman and Wakefield reports a region-wide Americas vacancy of 3.8% for H1 2026, with 91.7% of new capacity committed before delivery (Cushman and Wakefield, Americas data center update H1 2026, Sep 14, 2026). Its figure is higher because it counts a broader set of markets than CBRE and JLL do, not because space is easier to find.
By market
| Market | What CBRE's H1 2026 data shows |
|---|---|
| Northern Virginia | Vacancy about 0.2%, 2026 capacity fully committed, preleasing into 2027 |
| Chicago | Vacancy 2.2%, no contiguous block of 5 MW or more available in 2026, next large projects late 2027 at the earliest |
| Hillsboro | Vacancy 0.21% |
| Dallas and Fort Worth | More than 765 MW under construction, about 95% preleased |
| Atlanta | Turnkey space preleased about a year before completion, build-to-suit about two and a half years ahead |
Source: Data Center Frontier on CBRE's H1 2026 market data, Aug 28, 2026.
For an enterprise buyer the practical effect is simple: in the large markets, a requirement that has not been signed 18 months ahead of need is competing for what is left after the preleases.
Five steps to a capacity plan
Whatever the tool, a defensible plan comes from the same five steps, in this order.
Baseline
Measure IT load at the UPS output or the PDUs, count racks and positions, and write down cooling capacity net of the redundant unit.
Organic growth
Pick a rate from your own history, then run a slower and a faster case beside it. Dell sized its estate in small, medium and large scenarios for this reason.
Step loads
Add the known arrivals: an AI pod, a consolidation from another site, a large application. Put each in the month it lands.
Headroom rules
Set the share of usable power and cooling you will not pass, and say which redundancy level the room has to keep.
Trigger dates
Turn the crossing month into the dates that matter: when to start the search, when the contract or the build has to be signed.
On-premises, colocation or hybrid: what the numbers point to
The run-out date is half of the decision. The other half is how long each way of adding capacity takes, and what you commit to when you choose it.
| Option | What you are buying | What sets the timeline | When it fits |
|---|---|---|---|
| Expand what you run | New UPS, cooling or switchgear in a room you already control | Equipment and utility lead times. Medium-voltage gear and generators can take 9 to 18 months (BICSI study guide, Oct 2026), and a new grid connection more than four years (JLL, Jan 2026). | The room has floor space and the utility feed has spare capacity |
| Move to colocation | Contracted kW in a provider's hall, usually with a minimum you pay for whether you use it or not | Committing 18 to 24 months ahead, by JLL's count. Fit-out of the space itself now takes months rather than weeks (CBRE, Aug 2026). | The runway is shorter than any build, or density outgrows the room |
| Hybrid | Keep steady load where it is and put growth or AI in colocation or cloud | Two sets of lead times, but each one smaller. The contract only has to cover the growth. | The existing room is sound but the forecast or the AI plan is not |
Uptime's 2026 survey found that, for the first time, more IT workloads run in third-party facilities (46%) than in enterprise-owned sites (44%), and respondents expect the gap to widen to 48% against 42% by 2028 (Uptime Institute 2026 survey, reported by Data Center Knowledge, Jul 31, 2026). Hybrid is no longer the unusual case.
Planning colocation capacity: reserve, use and expand
When the forecast ends in a colocation contract, three numbers decide whether the contract fits it: what you commit to, what you will actually draw in the first years, and what you can add later without starting over.
Committed power against used power
Providers sell power by the kW and usually bill a minimum whatever you draw. CBRE puts take-or-pay floors at 60% to 85% of the power a tenant is allocated (CBRE, North America Data Center Trends H1 2026, Aug 27, 2026). A contract sized to your year-five load, signed when you draw a third of it, pays for idle power for years. The planner's colocation readout runs this comparison for your own numbers once the full forecast is open.
How far ahead to sign
JLL reports tenants committing 18 to 24 months before need (JLL midyear 2025 data, reported by CoStar, Aug 18, 2025) and, by midyear 2026, contracting for deliveries in 2028 (JLL, North America data center midyear 2026 release, Aug 11, 2026). Fit-out is getting longer too: CBRE says ready-for-service dates for fitted space have moved from weeks to several months, and converting a hall from air to liquid can add more than six months (CBRE, North America Data Center Trends H1 2026, Aug 27, 2026).
Room to grow without moving
Ask for growth to be written into the first contract: first refusal on the suite or cage next door, a reserved block held for a set period, or committed power that steps up on dates you choose. Each one costs something, and each is cheaper than a second migration.
Questions to put to a provider
- What density does the hall support per rack, in writing, and with what cooling?
- What is the take-or-pay minimum, and does it step up with the committed kW or start at the full figure?
- When is the space ready for service, and what dates does that depend on?
- What escalator applies each year? JLL says most new leases carry 3% or more (JLL, North America data center year-end 2025 release, Feb 17, 2026).
- What expansion rights come with the contract, and for how long?
What the capacity desk does with your forecast
The planner is run by the capacity desk at Metro Colo Advisory, which works for buyers of data center capacity. When a forecast comes in, we check it against measured data and the market, then tell you plainly where it stands.
- Forecast review. We test your baseline, growth rate, AI plan and headroom policy, and mark the inputs that would move the run-out date most.
- Colocation search. We take the forecast to providers that can deliver its size and density in the markets you name, on the dates the decision window allows.
- AI deployment planning. We size the GPU footprint, the cooling it needs and the places that can take it.
- Full capacity plan. A written plan for the estate: baseline, scenarios, trigger dates and the options that fit them.
If the forecast ends with a move into colocation and we place you there, the facility pays our fee. A forecast review or a capacity plan with no placement behind it carries a fixed fee, agreed and signed off in writing before any work begins.
Requests with a target year and a budget in place are answered first. Earlier-stage requests still get a reply, with the questions to settle before a search is worth starting.
Guides behind the planner
- Capacity planning template for Excel
The same forecast as a workbook, with a worked example and every formula written out.
- Capacity planning software compared
Spreadsheets, DCIM and simulation side by side, and when you need none of them.
- Power capacity planning
kW, kVA and amps, the 80% rule for rack circuits, 2N math and stranded power.
- kW per rack and rack density
Why the surveys disagree, what each density needs for cooling, and how to measure yours.
- AI data center capacity planning
Sizing a GPU footprint, the liquid cooling threshold and where enterprise AI can go.
- About the capacity desk
Who runs this site, how the planner was built and how we are paid.
Questions about data center capacity planning
What is data center capacity planning?
Working out how much power, cooling and floor space your IT load will need over the next one to five years, comparing that with what your room or contract can carry, and setting the dates by which you must act. The output that matters is a date: the month a limit is reached, and the earlier month by which a new contract or a build has to be under way.
How do I forecast data center power needs for the next five years?
Start from measured IT load at the UPS output or the rack PDUs, not nameplate. Grow it by an annual rate you can defend, add planned AI or other large deployments as step loads in the month they arrive, then compare each year with usable capacity at your redundancy level and a headroom line. The planner on this page does exactly that, month by month.
How much headroom should a data center keep?
Most teams plan never to pass 70% to 85% of usable capacity. The BICSI study guide describes warning at 70%, alerting at 80% and treating 85% as critical, and it notes that no standard fixes these percentages (BICSI DCDC study guide, continuous capacity management chapter, Oct 2026). The planner defaults to 80% and lets you set anything from 70% to 85%.
How far in advance should we reserve colocation space?
Plan to commit 18 to 24 months before you need the space. JLL reports that tenants who used to sign 6 to 12 months ahead now sign 18 to 24 months ahead (JLL midyear 2025 data, reported by CoStar, Aug 18, 2025), and its midyear 2026 release says tenants signing today are contracting for 2028 deliveries (JLL, North America data center midyear 2026 release, Aug 11, 2026).
What is a take-or-pay minimum in a colocation contract?
A floor on what you pay for power, set as a share of the power allocated to you, whether or not you draw it. CBRE puts these floors at 60% to 85% of the power a tenant is allocated (CBRE, North America Data Center Trends H1 2026, Aug 27, 2026). It is why sizing the first contract to the forecast, with expansion rights, usually beats signing for the five-year peak on day one.
What happens when a data center runs out of power?
New load waits, and the load you already run loses its margin. In a 2N room each path is meant to carry the whole load alone, so once load passes half the installed total a single path failure can no longer be absorbed. Power problems already lead outage causes: in Uptime's 2026 survey, power failures caused 56% of impactful outages (Uptime Institute 2026 survey, reported by Network World, Jul 30, 2026).
Should we expand on-premises or move to colocation?
Compare the runway with the lead time. If the forecast crosses your headroom line sooner than new utility power and gear can arrive, which JLL puts at more than four years for a new grid connection in primary markets (JLL, 2026 Global Data Center Outlook, Jan 5, 2026), colocation or a hybrid split is usually the only option that lands in time. If the room has spare utility capacity and floor space, expanding in place can be faster.
How is this site paid?
If the forecast ends with a move into colocation and we place you there, the facility pays our fee. A forecast review or a capacity plan with no placement behind it carries a fixed fee, agreed and signed off in writing before any work begins.